Parramatta Light Rail – Major Milestone Reached
January 2021 has seen the pouring of the first track in Eat street between the Lennox Bridge and Phillip Street. Construction crews are working a combined 8,500 hours a day/night and 166m of track has been installed. Fun fact: Construction crews will use aluminothermic welding to fuse sections of rail. The welding process uses…